I-76 Viaducts

Construction Schedule

I-76 Viaduct Repairs

PROJECT INFORMATION

CONSTRUCTION SCHEDULE

Repair Area shown in red. Google Earth imagery

PennDOT is currently revising the Schedule for 2020 repairs and related lane restrictions and closures that will take place beginning in early Spring. Updated information will be posted on this website each week as it becomes available.

The scope of the work being done on the viaduct and bridges includes all of the original work items as well as several additional repairs or improvements that have been added.  However, the original schedule of allowable lane restrictions and full closures is being re-evaluated and expanded to include additional daytime and overnight lane closures and more weekend full closures than originally planned in order to take advantage of significantly reduced traffic volumes resulting from the the COVID-19 crisis.

  Proposed Weekend and Overnight Closures
I-76 Eastbound ClosuresI-76 Westbound Closures
When Construction PhaseUniv Ave
Exit 346B
South St
On Ramp
South St
Exit 346A
Walnut St
On Ramp
Univ Ave
I-76 West
On Ramp
South St
Exit 346A
South St
On Ramp
30th St
Exit 345
Vine Expy
676 East
Exit 344
Spring 2019 – Dec 2020
Pre-Stage 1
April thru July 2019
Stage 1
July thru Oct 2019
Stage 2
April thru July 2020
Stage 3
July thru Oct 2020
Stage 4
  

I-76 viaduct repairs scheduled over a two year period in four stages.  

 

April thru July 2019

 

July thru Oct 2019

 

April thru July 2020

 

July thru Oct 2020

 

Spring 2019 – Dec 2020

Under Structure: Traffic impacts consist of I-76 WB right lane closure during overnight hours. One of the following ramps may be closed during these hours: University Avenue I-76 West On Ramp; South Street On Ramp; 30th Street Exit 345.

Eastbound and Westbound On-Off Ramps within the project limits may be closed during the Allowable schedule.

       Allowable Days and Times of Lane Closures or Full Closures

  • Weekday Nighttime Single Lane Closures Eastbound or Westbound

    Monday nights through Friday mornings: 9:00 PM to 5:00 AM
  • Weekday Nighttime Full Closures Eastbound or Westbound
    Monday nights through Friday mornings: 11:00 PM to 5:00 AM
  • Weekend Nighttime Single Lane Closures Eastbound or Westbound
    
Friday nights through Sunday mornings: 9:00 PM to 10:00 AM 

    Sunday nights through Monday mornings: 9:00 PM to 5:00 AM
  • Weekend Daytime Single Lane Closures Eastbound*
    Saturday mornings at 10:00 AM to Saturday nights at 10:00 PM 

    Sunday mornings at 10:00 AM to Sunday nights at 9:00 PM
  • Weekend Nighttime Full Closures Eastbound**
    Friday nights at 11:00 PM through Saturday mornings at 10:00 AM

    
Saturday nights at 10:00 PM through Sunday mornings at 10:00 AM 

    Sunday nights at 9:00 PM through Monday mornings at 5:00 AM
  • Weekend Daytime Single Lane Closures Westbound*
    Saturday mornings at 10:00 AM to Saturday nights at 10:00 PM 

    Sunday mornings at 10:00 AM to Sunday nights at 11:00 PM
  • Weekend Nighttime Full Closures Westbound**
    Friday nights at 11:00 PM through Saturday mornings at 10:00 AM 

    Saturday nights at 10:00 PM through Sunday mornings at 10:00 AM

    Sunday nights at 11:00 PM through Monday mornings at 5:00 AM 

* Anticipated weekend daytime single lane closures is ten times eastbound and ten times westbound.

** Anticipated weekend overnight full closures is ten times eastbound and ten times westbound.  